Quick answer
How long does a container of shisha charcoal take from deposit to loading on board?
Lead time runs from deposit to loading on board, includes the weathering window the carriage rules require, and the log shows each past container's dates. For these coconut shell charcoal briquettes the planning figures on file are 21 days of production for a 20 ft container, 14 days of weathering and 14 days from packing to on board.
| Date | Order | Container | Deposit to production start (days) | Production (days) | Production finished to packing (days) | Packing to on board (days) | Deposit to on board (days) | Loading port |
|---|---|---|---|---|---|---|---|---|
| Sep 2026 order (number masked) | 1 × 20 ft | 3 | 8 | 17 | 7 | 35 | Semarang |
Method: Dates from the order file of each container: deposit received, production start, production finished, packing and loading on board; one row per container, with the buyer and the order number masked.
Last updated 2026-10-06 · re-checked at least every 90 days · next due by 2027-01-04.
1. What the lead time counts
The lead time counts the days from the deposit received to the container loaded on board at the port of loading.
Definition
lead time
Lead time is the number of days from the deposit on a container order to loading on board, made up of production, drying, weathering before packing, and packing with documents.
It does not count the quotation, the sample or the ocean transit. The days at sea are recorded voyage by voyage on the transit times page, and a container order starts its count when the deposit arrives.
How facts on this page are confirmed is set out in the editorial and review policy.
2. Lead time by stage
The factory plans a container in three stages after the deposit: production, weathering and packing to loading.
| Stage | Planning figure |
|---|---|
| Production, 20 ft container | 21 days |
| Production, 40 ft container | 21–25 days |
| Weathering before packing | 14 days |
| Packing to loading on board | 14 days |
The weathering stage cannot be shortened, because weathering before packing is a carriage condition for charcoal at sea; the days are recorded for each container.
Special provision 978 sets carriage conditions for UN 1361 charcoal; it is not an exemption. Unless the competent authority approves otherwise, the material is weathered under cover for at least 14 days before packing (or steam-treated and packed under inert gas), packed at no more than 40 °C, and stowed with at least 30 cm of headspace, and the dangerous goods document states the production date, packing date and packing temperature.
Source: Resolution MSC.556(108): Amendments to the IMDG Code, special provision 978 and 5.4.1.5.18 (opens in new tab), International Maritime Organization (IMO), accessed
3. Where box printing sits
On an order in your own printed boxes, the box print is a stage of its own, timed from the approved artwork.
Printed boxes take 2 weeks from the approved artwork for a new design, and about 2 weeks for an existing one. So on a first order of your own design, the day the artwork is approved matters as much as the day the deposit arrives.
How the artwork is prepared and the proof approved is on the private label page.
4. The log of past containers
The log sits at the top of this page, one row per container, with the days of each stage taken from the order file.
The newest row (1 × 20 ft, loaded at Semarang) took 35 days from deposit to on board: 3 days to the start of production, 8 days of production, 17 days from the end of production to packing and 7 days from packing to on board.
The planning figures are the factory's working estimates for a new order; the log shows what each past container took. Read the two together: a figure in the plan and a row in the log are not the same thing.
5. What moves a lead time
A lead time moves with the artwork, the calendar and the space on the ship; the weathering window never shortens.
Note
What can move the loading date
- Artwork approval. On a printed order, a late approval moves the boxes and so the packing.
- Closures. The factory stops for Idul Fitri (Lebaran) and national public holidays; the dates are on the holiday and production calendar.
- Peak seasons. Production slots go to orders in the order they are confirmed.
- Space on the ship. On record, one booking was declined, by Maersk in July 2026, because the sailing had no dangerous goods space; it was rebooked on ONE 6 days later.
Why the weathering days sit inside every lead time is shown container by container in why 14 weathering days are inside every lead time, and the dates to order by for each market and season are on the order-by dates these lead times produce.
Questions buyers ask
Why is the weathering window inside every lead time?
Does the lead time include ocean transit?