Production Capacity and Planning: Monthly Capacity, Slot Allocation and Peak Periods

This page states how much the factory can make in a month, and is written for a buyer planning the volume and timing of shisha charcoal, the hookah charcoal or hookah coals of US and Canadian buyers. It gives one dated capacity figure, the arithmetic behind it in containers, and the rule by which production slots are given out.

Written by
Henry Sinaga
Reviewed by
Dimas Setyawan,
Updated
Reading time
4 min read

Quick answer

How much can this factory produce a month, and how is that capacity allocated between orders?

Production slots go to orders in the order they are confirmed, and monthly capacity is published with its confirmation date. The stated capacity is 260 t / month, confirmed November 2026, which is about 13–14 containers of 20 ft or 9 of 40 ft of coconut shell charcoal briquettes. Before Ramadan and the summer season, the factory asks for confirmation 6–8 weeks earlier.

Capacity and planning at a glance

As confirmed, November 2026

Monthly capacity
260 t / month, confirmed November 2026; reviewed every 90 days
Producing since
2020
Production time per container
21 days for a 20 ft; 21–25 days for a 40 ft
Weathering
14 days
Slot rule
Production slots go to orders in the order they are confirmed
Order types
Order by order and a repeat program with reserved capacity

1. What production capacity is, and the stated figure

Capacity is one figure with a date on it, and the panel at the top of this page states it.

Definition

production capacity

Production capacity is the quantity of finished briquettes a factory can produce in a stated period, given here in metric tons per month.

The stated capacity is 260 t / month, confirmed in November 2026. The figure is the owner's statement, reviewed on a fixed interval, and this page changes when it does.

How facts on this page are confirmed is set out in the editorial and review policy.

2. What the capacity means in containers

In containers, the capacity is the monthly tonnage divided by the load of one container.

Containers a month at this factory's stated production capacity, calculated as capacity divided by the load per container and rounded down; capacity confirmed November 2026, loads by shape on the products pages.
ContainerLoad per containerContainers a month at the stated capacity
20 ft 18.5–20 t13–14
40 ft 26.5 t9

Note

A ceiling, not an offer

The result is the ceiling across all orders in a month, not the capacity open to a new order. Which container suits an order is on the 20 ft or 40 ft page, and a container order is always at least one container.

3. How capacity is allocated between orders

Slots are given out by one rule, and a repeat program is the one way to hold capacity ahead.

The rule: production slots go to orders in the order they are confirmed.

  • Order by order.
  • A repeat program with reserved capacity: the buyer commits to a minimum quantity in a set period, for example one container every two weeks.

In a program, capacity is reserved 8 weeks ahead, and the price follows the monthly price list. The steps of an order are on the ordering page.

4. Peak periods and closures

Capacity is tightest before two peaks, and production stops for the holidays.

  • Peaks: before Ramadan and the summer shisha season; confirm orders 6–8 weeks earlier than usual.
  • Stops: Idul Fitri (Lebaran) and national public holidays, with dates set by the factory for Idul Fitri and by the government decree (SKB 3 Menteri) for national public holidays, each year.
  • Closed days: national public holidays and collective leave (cuti bersama).

No date is typed on this page. The order calendar gives the order-by dates the peaks produce, and the closures are listed in the production calendar, on the Indonesian holidays page.

5. How capacity relates to lead time

Capacity sets how many orders fit in a month; lead time is how long one order takes.

Production takes 21 days for a 20 ft container and 21–25 days for a 40 ft, followed by 14 days of weathering and 14 days from packing to on board. The lead time page is where lead times under normal and peak load are published as they are logged.

Note

Not on file yet

  • The number of lines and shifts.
  • Daily output.
  • Lead time under peak load.

Questions buyers ask

How many containers a month is the stated capacity?
At the stated capacity of 260 t / month and loads of 18.5–20 t per 20 ft container or 26.5 t per 40 ft container, the arithmetic gives about 13–14 containers of 20 ft or 9 of 40 ft a month. That is the ceiling across all buyers, not the quantity open to one order.
Can capacity be reserved for repeat orders?
Yes. Besides order-by-order buying, the factory offers a repeat program with reserved capacity. The program asks for a minimum quantity in a set period, for example one container every two weeks. Capacity is reserved 8 weeks ahead, and the price follows the monthly price list; outside a program, slots go to orders in the order they are confirmed.
When is capacity tightest?
Capacity is tightest before Ramadan and in the summer shisha season. For those peaks the factory asks buyers to confirm orders 6–8 weeks earlier than usual. Production also stops for Idul Fitri (Lebaran) and national public holidays. The order calendar gives the order-by dates these periods produce.

See the factory for yourself

Video audit on request; third-party inspection by the agency of your choice.