Quick answer
How much can this factory produce a month, and how is that capacity allocated between orders?
Production slots go to orders in the order they are confirmed, and monthly capacity is published with its confirmation date. The stated capacity is 260 t / month, confirmed November 2026, which is about 13–14 containers of 20 ft or 9 of 40 ft of coconut shell charcoal briquettes. Before Ramadan and the summer season, the factory asks for confirmation 6–8 weeks earlier.
Capacity and planning at a glance
As confirmed, November 2026
- Monthly capacity
- 260 t / month, confirmed November 2026; reviewed every 90 days
- Producing since
- 2020
- Production time per container
- 21 days for a 20 ft; 21–25 days for a 40 ft
- Weathering
- 14 days
- Slot rule
- Production slots go to orders in the order they are confirmed
- Order types
- Order by order and a repeat program with reserved capacity
1. What production capacity is, and the stated figure
Capacity is one figure with a date on it, and the panel at the top of this page states it.
Definition
production capacity
Production capacity is the quantity of finished briquettes a factory can produce in a stated period, given here in metric tons per month.
The stated capacity is 260 t / month, confirmed in November 2026. The figure is the owner's statement, reviewed on a fixed interval, and this page changes when it does.
How facts on this page are confirmed is set out in the editorial and review policy.
2. What the capacity means in containers
In containers, the capacity is the monthly tonnage divided by the load of one container.
| Container | Load per container | Containers a month at the stated capacity |
|---|---|---|
| 20 ft | 18.5–20 t | 13–14 |
| 40 ft | 26.5 t | 9 |
Note
A ceiling, not an offer
The result is the ceiling across all orders in a month, not the capacity open to a new order. Which container suits an order is on the 20 ft or 40 ft page, and a container order is always at least one container.
3. How capacity is allocated between orders
Slots are given out by one rule, and a repeat program is the one way to hold capacity ahead.
The rule: production slots go to orders in the order they are confirmed.
- Order by order.
- A repeat program with reserved capacity: the buyer commits to a minimum quantity in a set period, for example one container every two weeks.
In a program, capacity is reserved 8 weeks ahead, and the price follows the monthly price list. The steps of an order are on the ordering page.
4. Peak periods and closures
Capacity is tightest before two peaks, and production stops for the holidays.
- Peaks: before Ramadan and the summer shisha season; confirm orders 6–8 weeks earlier than usual.
- Stops: Idul Fitri (Lebaran) and national public holidays, with dates set by the factory for Idul Fitri and by the government decree (SKB 3 Menteri) for national public holidays, each year.
- Closed days: national public holidays and collective leave (cuti bersama).
No date is typed on this page. The order calendar gives the order-by dates the peaks produce, and the closures are listed in the production calendar, on the Indonesian holidays page.
5. How capacity relates to lead time
Capacity sets how many orders fit in a month; lead time is how long one order takes.
Production takes 21 days for a 20 ft container and 21–25 days for a 40 ft, followed by 14 days of weathering and 14 days from packing to on board. The lead time page is where lead times under normal and peak load are published as they are logged.
Note
Not on file yet
- The number of lines and shifts.
- Daily output.
- Lead time under peak load.